Phase 1 and Phase 2 Map for ODWW Project

ODWW Project Map

The Out of District Wastewater (ODWW) Project has been broken down into Phase 1 and Phase 2. Phase 1 consists of approx. 330 locations around the Live Oak Golf Course with work laying the main lines beginning May 2019. Homes in this area are expected to begin being offered the option to hook up to this new system starting in summer 2021. Phase 2 consists of an additional approx. 900 locations and will begin after Phase 1 has been completed in approx. early 2024. A project timeline can be found here.

The Early Connection option remain open to select homeowners who qualify. Contact Us for details.

Please see our Coverage Area page for more maps from Lakeway MUD (LMUD).

Phase 1 encompasses area with solid green shading. Phase 2 encompasses area with green stripped lines.